Summary of work carried out
12 luminaires along the park paths and 4 on the dog training area. New lighting calculations, a new technical solution and new luminaires. The solution was agreed with the municipality before work started, followed by installation, testing and handover documentation.
Work we carried out:
- Working drawings — drawings and technical specifications prepared before work started
- Agreement with the municipality — the solution and the choice of luminaires were approved by the client before installation began
- New lighting calculations — illuminance levels and uniformity recalculated because the luminaires were changed
- New lighting calculations — illuminance levels and uniformity recalculated because the luminaires were changed
- External cable route installation — cables laid on a sand bed with warning tape, records of concealed works completed before backfilling
- Luminaires and lighting columns — foundations, columns, luminaires and their installation
- Earthing installations — earth electrode, connections and protective bonding
- Testing — insulation resistance, earth fault loop impedance, continuity of protective conductors and earth electrode resistance
- Handover records and documentation — as-built drawings, test reports and the handover record for the client
- Inspection — carried out by an independent accredited inspection body